Why Planning Makes or Breaks a Commercial Paving Project
A commercial paving project that goes smoothly is one that was planned thoroughly before a single piece of equipment showed up on site. A project that goes badly almost always has the same root cause: insufficient planning.
Rushed projects lead to missed permits, unexpected costs, poor scheduling during Oregon's limited dry season, and results that do not hold up. Taking 4-6 weeks to plan properly saves you money, headaches, and a parking lot that fails prematurely.
This checklist walks you through every step of planning a commercial paving project, from initial assessment through project completion.
Phase 1: Assessment and Goal Setting (Weeks 1-2)
Define the Project Scope
Before contacting contractors, clearly define what you need:
- [ ] Identify the problem. Is this maintenance, rehabilitation, or full replacement?
- [ ] Measure the area. Calculate total square footage of the project area
- [ ] Document current conditions. Photograph all damage, drainage issues, and problem areas
- [ ] List must-haves vs. nice-to-haves. Separate essential repairs from optional upgrades
- [ ] Determine if layout changes are needed. Adding spaces, changing traffic flow, ADA upgrades
Assess the Existing Pavement
Understanding what you are working with determines the right approach:
- [ ] Surface condition: Rate the severity of cracking, potholes, and surface deterioration
- [ ] Base condition: Look for signs of base failure including alligator cracking, heaving, and depressions
- [ ] Drainage performance: Note any areas with standing water or poor drainage
- [ ] Pavement age: Check original construction records if available
- [ ] Previous repairs: Document patches, overlays, and other past work
If you are unsure whether to overlay or replace, request a core sample analysis. A contractor drills 4-inch cores at several locations to measure pavement thickness and assess base condition.
Set Your Budget Range
Establish a realistic budget before soliciting bids:
| Project Type | Cost Range (per sq ft) | 10,000 sq ft Lot | |-------------|----------------------|------------------| | Sealcoat + crack seal | $0.20-$0.50 | $2,000-$5,000 | | Overlay (resurfacing) | $1.50-$3.50 | $15,000-$35,000 | | Mill and overlay | $2.50-$5.00 | $25,000-$50,000 | | Full replacement | $3.00-$7.00 | $30,000-$70,000 | | New construction | $4.00-$9.00 | $40,000-$90,000 |
Add 10-15% contingency for unexpected conditions discovered during construction. Budget separately for striping, signage, landscaping, and stormwater work.
Phase 2: Permits and Compliance (Weeks 2-4)
Check Permit Requirements
Contact your local building department to determine what permits are needed:
- [ ] Building permit for new construction or significant modifications
- [ ] Grading permit if earthwork exceeds local thresholds
- [ ] Stormwater permit if altering drainage or adding impervious surface. See our stormwater management guide.
- [ ] Right-of-way permit if work affects public sidewalks, roads, or utilities
- [ ] Environmental permits for projects near wetlands, streams, or protected areas
Verify ADA Compliance
Any alteration that affects the parking lot's usability triggers ADA requirements:
- [ ] Calculate required accessible spaces based on total lot capacity
- [ ] Verify accessible route from parking spaces to building entrance
- [ ] Check slope requirements (max 2% in any direction for accessible spaces)
- [ ] Plan signage including post-mounted signs and pavement markings
- [ ] Identify van-accessible spaces with wider access aisles
Review Stormwater Requirements
Oregon cities along the I-5 corridor have specific stormwater management standards that may apply to your project:
- [ ] Determine if your project triggers stormwater requirements (varies by city)
- [ ] Identify required best management practices (bioswales, detention, treatment)
- [ ] Budget for stormwater improvements if required
- [ ] Plan for erosion control during construction
Phase 3: Contractor Selection (Weeks 3-5)
Solicit Bids
Get at least three written bids from qualified paving contractors:
- [ ] Request detailed written proposals that specify materials, quantities, and methods
- [ ] Verify contractor licenses through the Oregon Construction Contractors Board (CCB)
- [ ] Check insurance certificates including general liability and workers compensation
- [ ] Request references from similar commercial projects completed in the last 2 years
- [ ] Ask about warranties for materials and workmanship
Evaluate Bids Properly
The lowest bid is not always the best value. Compare bids on these criteria:
| Evaluation Criteria | What to Look For | |--------------------|-----------------| | Material specifications | Asphalt mix type, aggregate base depth, compaction standards | | Scope completeness | Does the bid include everything? Mobilization, striping, cleanup? | | Timeline | Realistic schedule with weather contingency days | | Payment terms | Progress payments tied to milestones, not just start/finish | | Warranty | Minimum 1-year workmanship warranty, material warranty terms | | Insurance | Current certificates with adequate coverage limits |
For a more thorough evaluation framework, see our guide on evaluating paving contractor bids.
Check References
Contact at least two references for your selected contractor:
- [ ] Was the project completed on time and within budget?
- [ ] How was communication throughout the project?
- [ ] Were any issues handled professionally?
- [ ] How does the pavement look 1-2 years later?
- [ ] Would you hire them again?
Phase 4: Pre-Construction Planning (Weeks 5-7)
Schedule the Work
Timing is critical for paving projects in Oregon:
- [ ] Book your contractor early. The May-October season fills up fast.
- [ ] Build in weather contingency days. Even summer months see occasional rain.
- [ ] Coordinate with tenants. Notify all affected businesses at least 2-3 weeks in advance.
- [ ] Plan phasing if the lot must remain partially open during construction.
- [ ] Schedule utility locates. Call 811 at least 2 business days before any excavation.
Plan for Business Continuity
Your parking lot will be partially or fully unavailable during construction:
- [ ] Identify alternative parking for customers and employees
- [ ] Create a traffic management plan for phased construction
- [ ] Notify customers through signage, email, and social media
- [ ] Coordinate delivery schedules to avoid conflicts with construction
- [ ] Arrange temporary signage directing customers to alternative access
Finalize the Contract
Before signing, confirm these items are in the contract:
- [ ] Detailed scope of work with material specifications
- [ ] Project timeline with start date, milestones, and completion date
- [ ] Total price with payment schedule tied to milestones
- [ ] Change order process for handling unexpected conditions
- [ ] Warranty terms for materials and workmanship
- [ ] Insurance requirements and certificates
- [ ] Cleanup and site restoration responsibilities
- [ ] Cancellation and dispute resolution terms
Phase 5: Construction Management (Project Duration)
Pre-Construction Meeting
Hold a meeting with your contractor before work begins:
- [ ] Walk the site together and confirm the scope
- [ ] Review the construction schedule day by day
- [ ] Establish communication protocols (daily updates, point of contact)
- [ ] Confirm equipment staging and material delivery locations
- [ ] Review safety requirements and site access restrictions
During Construction
Stay engaged throughout the project:
- [ ] Monitor daily progress against the schedule
- [ ] Document everything with daily photos and notes
- [ ] Address issues immediately rather than waiting for completion
- [ ] Verify material quality by requesting delivery tickets for asphalt loads
- [ ] Watch for compaction and make sure the contractor is testing density
- [ ] Inspect base preparation before asphalt is placed (this is your last chance to catch problems)
Quality Checkpoints
Key moments to inspect the work:
- After demolition/removal: Verify the subgrade condition before base installation
- After base installation: Check base thickness and compaction before paving
- During paving: Monitor asphalt temperature, lift thickness, and roller patterns
- After paving: Check final grades, smoothness, and drainage flow
- After striping: Verify ADA compliance, line accuracy, and marking clarity
Phase 6: Project Closeout
Final Inspection
Walk the completed lot with your contractor:
- [ ] Verify all work matches the contract scope
- [ ] Check drainage by observing water flow during rain or hosing
- [ ] Inspect transitions between new and existing pavement
- [ ] Confirm all striping is accurate and ADA-compliant
- [ ] Note any punch list items for correction
Documentation
Collect and file these documents:
- [ ] Final invoice and proof of payment
- [ ] Warranty documentation
- [ ] As-built drawings (if applicable)
- [ ] Material delivery tickets and test reports
- [ ] Permit closeout confirmation
- [ ] Contractor contact information for warranty claims
Start Your Maintenance Program
Your new or resurfaced parking lot needs a maintenance program from day one. Develop a plan that includes sealcoating, crack sealing, and regular inspections. See our guide on creating a pavement maintenance plan for details.
Get Your Commercial Paving Project Started
Cojo Excavation and Asphalt guides commercial property owners through every phase of the paving process, from initial assessment through project completion. We serve properties along Oregon's I-5 corridor from Portland to Eugene, and our team handles projects of all sizes.
Call 541-409-9848 or request a free project consultation to get started.
Get a Free Quote
Tell us about your project and we'll get back to you within 24 hours.